Emergency DPCC Compliance in 3 Days — 1,800 sqm Apartment Block, Noida

Client
Confidential developer
Site area
1,800 sqm
Duration
3 days end-to-end

The challenge

Stop-work notice issued by UPPCB citing missing AQI sensor, no PTZ camera live feed and incomplete dust-control. Project facing ₹50,000/day environmental compensation.

What we did

  • Same-day site audit and gap report shared on WhatsApp within 4 hours
  • Mobilised 50m anti-smog gun + perimeter sprinklers next morning
  • Installed CPCB-listed AQI sensor with live DPCC API push by day 2
  • PTZ cameras commissioned, RTSP feed integrated and tested with the zonal officer by day 3
  • Filed point-by-point notice response with geotagged photo evidence

Outcome

  • Notice closed in 6 days from issue date
  • Zero further environmental compensation
  • Site retained on monthly compliance AMC since 2024

"We were threatened with site stoppage. Garg Infratech resolved everything in 3 days — truly emergency response at its best."